Baths reopening now scheduled for mid-Jan

Here is Cllr Mullaney’s latest update on work to the Baths, dated 29th September.

I attended a meeting this afternoon with the contractors who will shortly start working on re-opening Moseley Road baths. The good news is that we are still on target to re-open the swimming baths in mid-January 2012.

My last blog update was on 25th August and can be seen at http://martinmullaney.blogspot.com/2011/08/update-on-moseley-road-baths-25th.html

The contractors will move onto site on 17th October and spend six weeks removing all asbestos from the basement. End date is 25th November.

From 25th November, work will begin on installing the permanent structural scaffolding in the basement which will replace heavily corroded temporary scaffolding which is holding up large sections of the floor plate of the building. This work will take six weeks to complete. Taking into account the Christmas break, we anticipate work finishes mid-January and the baths re-opening.

On top of this work, I have successfully bid for money from the Council’s corporate centre to do the following:

£50,000 to prepare a Heritage Lottery bid for just over £5million for phase one of the works to restore these baths.

£80,000 for ‘sticking plaster’ works to get the swimming baths through the next two years, in preparation for any restoration monies. The ‘sticking plaster’ works have still to be finalised, but we hope these will include minor roof repair works, installation of missing rainwater guttering and a boiler service.

Leave a Reply