Update on Moseley Road baths – 26th February 2012.
Work on the final phase to get Moseley Road baths re-opened in April is well under way.
Followers of the present saga to get these historic baths re-opened will be aware of how much hair I’ve been pulling out over this issue. What started out as a six week closure in December 2010 for a simple lintel replacement, escalated as health and safety found more and more issues to prevent its re-opening.
Each issue has been resolved and we are now on the final piece of work to remove all the flaky paint from the ceiling of Pool 2 and to replace all the stolen roof lead.
For more on the flaky paint issue, please read my blog report at http://martinmullaney.blogspot.com/2012/02/moseley-road-baths-re-opening-delayed.html
For more information on the stolen roof lead, please see my other blog report at http://martinmullaney.blogspot.com/2011/11/update-on-moseley-road-baths-19th.html
As you will see from the attached photos of the interior of Pool 2, the erection of the scaffolding is nearly complete. The scaffolding will be complete on Wednesday 29th February – one and a half weeks ahead of schedule.
Removal of the flaky paint using a special epoxy resin will begin straight away. A specially developed Dulux paint for use in a high humidity atmosphere will be applied. Flaky paint removal and repainting will take three weeks.
Removal of the scaffolding will then take 10 days.
Replacement of all stolen lead with a lead substitute will take place in parallel. Also, using the knowledge of the pools staff, efforts will be made to get rid of other roof leaks.
We estimate that all work will be complete by 4th April. The pools re-opening will then be based on how long it takes to refill the pool.